DNJ Management commend the Leaders and Team members involved in successfully completing the Testing and Commissioning of AADC A12840 Al Shabahat 33/11kV Primary Substation and Ndood Jham 33/11kV Primary Substation under our Client M/s ABB Industries LLC in last quarter of 2019.

The full team had extended timely service with professional approach for the mentioned activities under the DNJ Leaders Mr. Zaffir and Mr. Balaji Jagadeesan.

While, the complete Commissioning was executed excellently by DNJ Team Leaders Eng. Ashok Soundarajan and Eng. Muthupandi. The appreciation also extends to team members Eng. Vignesh, Eng. Kathiravan, Eng. Hajim Basha, Eng. Amthan Ali and Eng. Hari.

Furthermore, DNJ Energy thank ABB Management and appreciate the support and technical guidance extended by Mr. Jayaram Venketesh of ABB Industries LLC, without which this mission would not have achieved in such a limited time period.